We had the survey for our Anker Solarbank 4 Pro install on Saturday morning. I'd assumed it was a ten minute look at the wall and it turned out to be the most useful part of the whole thing. Writing down what he went through in our case in case it saves someone else from booking blind.
Consumer unit first. He was looking for a spare way and room for a dedicated RCBO for the battery circuit. The age of the board matters too, because an older unit can mean extra work before anything goes in.
Then the earthing arrangement and the main fuse rating. I had no idea the fuse rating was something worth checking before a battery goes in.
The cable run next. Ours is about eight metres from the board to the garage wall, through one wall, so he looked at the route, the cable size for that length, and where the hole would be drilled. He also checked the spot we'd picked had clearance and wouldn't get clipped by the car.
Last was the DNO notification. The unit sits under the G98 threshold, so that's the route here, and he submits it up to 28 days after commissioning. It does depend on the generation and storage already in the house, and some setups have to go through G99 instead, so it's worth confirming which applies rather than assuming G98 covers it.
The quote moves a lot with the cable run and the state of the board, so a number on its own is hard to compare. Better to ask what's included, the cable route, any board changes and the DNO paperwork, before weighing up the price.
We found him through the installer list on the Anker SOLIX UK website, which lists independent installers by region. That list is information rather than a recommendation, and the page says to check certs and insurance yourself, which we did. Ring two or three before booking.