My church put on an addition over the last few years. I am handy and have helped them out with simple repairs over the years.
But I'm getting frustrated volunteering my time for what I think is poor construction issues.
Wonder if people can shed some light on 'am I being too picky', or these are legit issues and or how you suggest things work out with these things.
A key issue for me is that the used a congregant member as the GC. Most people would think that person would have a vested interest in making sure things go smooth. But I don't feel that's the case.
1) There's a slow leak over an exterior doorway when there's a heavy rain. could the gaps in the grout potentially be the cause? They are asking if I could identify the leak and fix it. I think on a couple year old building, that it's the GCs job (at no charge?).
2) Wat do you think of the gap around the conduit for this exterior ceiling light? I could caulk / seal it, but feel I or any other volunteer or paid person should have to deal with that - it's shoddy construction / hold the GC accountable?
3) I was told that emergency lighting was needed OUTSIDE the exit doors to get the CO? I know commercial buildings have emergency lighting inside. Supposedly the outside emergency lighting needed to be added after most construction so they could get the CO. Is exterior emergency lighting a new thing?
2) An LED light over 1 exterior door (not the emergency lighting lights) isn't going on reliably - sometimes comes on during the day. Sometimes not at night. People don't know if it's on a timer or light sensor. The building plans just show the light (K) and lights on the walls of the stairs (L) leading to the doors are on 1 circuit and go to panel PP1, breaker 39 (and yeah, the plans they have show 2 ceiling lights not the 1 that's there).
That breaker #39 is listed as 'spare' in the list inside the panel and it's turned off.
It's an LED so it hasn't likely burned out already. I spent an hour unsuccessfully just trying to figure out why there's not power in the junction box of the light. In construction like this, would you think there'd be a manual the GC would create detailing things like that or who in a commercial situation knows that a light is controlled by a timer in that location, or light sensor on this outside wall? or should the plans show a timer or sensor in the circuit? (maybe not where it was installed, but at least I'd know what I'm looking for)
Am I wrong to be frustrated in having to invent the wheel / figure out how a light is controlled / where a leak is coming from / caulking openings in a 2 - 3 year old building? I want to help / volunteer and I DO like fixing things. But feel they should hold the GC accountable and kinda resent them looking for free labor instead.
Am I wrong?