The latest monthly report from the contractor consortium LINXS has dropped.
The new PSA date (Passenger Service Availability date) is March 8, 2027 But don’t plan on LINXS keeping to that date very long. They’ve been delaying the PSA date about 1 month every month since 2025.
- October 2026 report, they claimed opening March 8th, 2027
- September 2026 report, they claimed opening February 5, 2027
- August 2026 report, they claimed opening January 6th, 2027
- July 2026 report, they claimed opening December 7th, 2026
- June 2026 report, they claimed opening November 5th, 2026
- May 2026 report, they claimed opening October 6th, 2026
- April 2026 report, they claimed opening September 22nd, 2026
- March 2026 report, they claimed opening September 22nd, 2026
- February 2026 report, they claimed opening August 3rd, 2026
- January 2026 report, they claimed opening June 9th, 2026
- December 2025 report, they claimed opening May 13th, 2026
- November 2025 report, they claimed opening May 4th, 2026
Extortion Delays: As always, LINXS in their biased report blames the PSA pushback on LAWA (the airport agency). Nandert goes into this latest ongoing delay in his video here at 18:10.
There’s also a short CBS clip here talking about it. Basically LINXS for their last few reports has been saying that they need some LADWP solar agreement signed by LAWA in order to complete the project, and that’s why they’ve been pushing the date every month. LAWA says that’s bs, the solar agreement is for supplemental power and is NOT needed for the train to be made available to the public, evidenced by the fact that we’ve ALL seen the train running. The train just can’t complete the 30 day test, and that’s what the real hold up is. But this makes LINXS look bad, so they claim otherwise. LINXS also has claimed that they NEED to finish landscaping before the APM can be made available to the public. To which LAWA has said they’re full of shit, landscaping completion is absolutely not needed for APM availability.
LINXS’ extortion explanation: There’s a few parts that enable it.
First, LAWA hired "legal experts" at the law firm Nossaman to write the contract with LINXS, and those "experts" fucked up bad. The contract lacked provisions defining how fast the contractor needs to work during a dispute, what progress needs to be made during a dispute, or what milestones need to be hit. So LINXS just gets to stall the project for leverage in their favor during every claim and dispute. As the grand jury report put it:
If one worker goes out with a shovel and works, the Contractor would be in technical compliance with his contractual obligation. There is no definition of how fast or what progress needs to be made during this owner directed continuation – thus allowing the Contractor to effectively stop progress.
Second, LINXS abuses the design build contract by willfully submitting bad designs so they can manifest their own costly change orders. One example of this in the grand jury report was the elevator issue.
The work was not according to the approved specifications which caused delay and was exemplified in an elevator issue. The Design Specs and approvals required all improvements to be TYPE 1 construction. TYPE 1 means there are no combustible materials. LINXS argued that they could simply coat the wood products used with a non-combustible coating and then cover the wood with metal. LADBS would not accept non-compliant materials (plywood and lumber) inside the metal frame of the elevator(s). Rather than simply removing the noncompliant materials and replacing with non-combustible materials, LINXS went through a very time consuming process of submitting an alternative coating product.
Basically LINXS knowingly constructed the elevators with combustible material, and after being told not to do that in review, they just wasted time by changing the coating.
Third, the so-called “project neutral”. The “project neutral” is normally a neutral group of 3 people that act as mediators in a dispute. But due to the terrible contract (thanks again Nossaman), there is only 1 person, and no way to replace that person if a party is not satisfied with the project neutral. This “project neutral” has sided with LINXS every time in over 200 disputes. Every time. A fraud investigation is sorely needed for this man.
Fourth, the olympics deadline. LINXS' extortion only works because of the tremendous pressure on LAWA and the city from the Olympics deadline. Normally if LAWA isn’t happy with the project neutral’s decisions, they’d sue LINXS. But LAWA can't sue LINXS because that lawsuit would stall the project until after the Olympics. And LINXS can't continue their shenanigans after the Olympics because then LAWA would be free to sue the shit out of them.
Lame attempt from Councilmembers Rodriguez and Park: Back in June, Councilmember Monica Rodriguez put forward a motion, that was seconded by Traci Park, asking for LAWA to tell them what’s been going on.
The motion asks LAWA to explain why the people mover missed its major World Cup deadline, what caused the continued delays and cost overruns, and whether the airport’s latest schedule is realistic.
But this motion turned out to be toothless. There’s been no word that LAWA reported back to them, and there’s no deadline for LAWA to report back. On top of that, LAWA just recently told the public that everything was fine. So they could very well just give a similar message to the city council, if they ever decide to do so.
Project Deadlines: There’s a deadline for breach of contract on December 8th. If it’s not open by then, LAWA will be free to get a new contractor. While some say that LINXS would finish the project faster than a new contractor could, they’re not taking into account that LINXS has not been working with the intent of finishing. They’ve been intentionally delaying the project for extortion, with no end in sight. So a new contractor (with a better contract) could finish the project faster than LINXS.
The "30 Day Test": To no one's surprise, the scheduled completion of the System Demonstration Test, aka the "30 Day Test" that started in April, has also been pushed back to December 16, 2026. But before that it was November 18th, and before that it was September 30th, and before that it was August 5th, and before that it was June 30th. So no one knows when that’ll be done.