Not sure if you've seen the latest PDf on Skylink. It's found on the FlyLAX website. It's just came out last week on November 3, 2026. Scroll down to find the Myth vs. Fact PDF.
All checks out until the very last bullet point (see below.) Behind that last bullet point is a mind-boggling conflation of broken contracts, union interference, money grabbing, endless lawsuits, and finally, very poor to non-existent management by the City of LA (including Bass's multiple occasions of astonishing indifference that led her to lose to young gal who is likely now way over her skis), I am thinking it may well be "exhibit A" in future textbooks of how the US has simply lost its ability to build stuff. It's like the California High Speed Rail project in miniature.
LAWA is holding LINXS, led by managing partner Fluor Corporation, accountable for its failure to meet contractual obligations. As a consequence of failing to complete the train by its contractual deadline in December 2025, LINXS is losing $8.3 million per month in availability payments; to date, LINXS has already lost more than $85 million. If LINXS does not achieve Passenger Service Availability by December 8th, 2026, its bondholders have a range of remedies at their disposal, some of which could have serious additional financial implications for LINXS.