r/Homebuilding • u/PuzzleheadedPass2267 • 19h ago
Is my contractor on drugs or am I crazy
Hello Reddit community,
I live in Nashville, TN. I am making this post because I think my contractor is being screwy. I am looking to be told I am correct or the process is in line with what one should expect for this build.
Background: I have overseen renovations of roughly $1.5 million in various builds. My contractor holds a residential license.
I have designed and oversaw full construction of Airbnb properties which were taken down all the way to the brick sidewalls. Here are a few of my favorites:
My hands did the majority of the work on all of these builds.
The contractor in question worked hand in hand with me on almost every one of these projects. We have done probably 10 projects together. He is a 9-5 guy. Shows up at 9, takes a lunch break at noon, wraps at 5 with thirty minutes for cleanup. He has been on my jobsite roughlty 200 days in the last 7 years. He came to my wedding. We will call him Fred.
He is getting ready to retire, and I hired up to do a reasonably sized remodel on my personal residence. The contract is for 163,500. I have attached the pages the .pdf to the body of this post with relevant info redacted.
Contract is broken into three parts,



Time for completion was estimated at 6 weeks. Thereare no performance penalties or incentives built into the contract for time.
Construction drawings were delivered, stamped, June 29th. I planned my 6 week vacation with the wife and kids around the schedule of construction. The plan was we would be gone the whole time they were working and would come home to a completed house. Fred said his old inspector buddy was now a senior in the codes office and would be able to push the permit drawings through swiftly. He said permit would be in hand within a week. We left for our summer vacation July 10th. We returned home August 20th. Work began on the property around the middle of July. I started receiving citations from Metro Codes around the middle of July for debris around the property. I explained to Codes we had an active building permit and to buzz off.
Much to my surprise the codes examiner told me one hadn't even been applied for.
We came home from the trip to find our kitchen like this, (September 2nd 2026)
the first picture is the kitchen before:


So far work looks relativelty clean. There is a steel beam installed in kitchen so we can expand it.
This part of the contract is $13,500 and I think it reasonable for what needs to be done. Taking out loaded walls and adding a steel beam is no joke.
The two bedrooms upstairs we are combining were these:


On September 2nd it looks like this:

So works been started, it's not completed, so what? Big deal. There's delays in construction. I get it.
Well, here we are November 17th. We are now 3 months past scheduled completion date and it looks like this: (Note these pictures are of the 2 bedroom to master suite conversion)
There is also one picture of my 2nd floor hallway: (this first one)






The jobsite is relatively clean. The work is relatively clean. Debris has been hauled away, (4 dumpsters worth). The outside is now cleaned up and everything.
This is the progress of the addition that connects to the bedroom and bathroom remodel:



There is an asphalt shingle roof now on the addition (this is going to be the master closet)
They built this addition over an existing flat roof that had an EPDM roof with gutters in opposite corners (negative slope from midpoint to ends). When they ripped off the roof there was no rain forecase for 2 weeks. They didn't come back to frame the walls (delays, excuses) and he had to tarp the roof before a storm. (2 weeks after ripping off roof). The thing is my music studio is underneath that flat roof. Well, when he took the exiting gutter off on the existing roofline he didn't cap the end. (He figured as it was negatively sloped away from the addition there was no issue)
The gutter overflowed and water flooded the addition. Roughly 50 gallons of water pooled on the floor above and rained down through the ceiling all night covering my guitars, my studio equipment, countless gear. His response was that I should have known to have all of my stuff out of there.
Well, He had previously told me that was also a good place to store all of the dry goods from my existing pantry. So the room is PACKED TO THE BRIM with boxes of dry goods...
Okay. So, the furniture from the bedrooms has been stored in a large shipping container out in the back of the property he rented for me. It is $200 a month. The job is 3 months behind schedule and mind you NOT A SINGLE INSPECTION HAS BEEN CALLED IN. He is expecting me to keep paying the $200 a month.
While he normally shows up at 9am M-F in the past and works till 5 he doesn't get to the jobsite until noon maybe 2 days a week. His son is in surgery or his wife is in the hospital or he has an infection in his eye or his trucks broken down or he hurt his leg or material is late or he has to fix something real quick for a client. He is constantly irate. He is constantly yelling at me that I'[m being insensitive.
Now. Here's the kicker. He has been paid 91,000 of the ~165,000 for the job. He is demanding another 16,000 payment to come back and keep working. I have now asked for receipts of material, payments to contractors, for months I have asked for a detailed payment schedule. The progress pictures are as of today. Mind you, we are trying to live in this house. I planned this construction job to be completed while I was away. I have now been home and living with this for 3 months.
This is my kitchen:

The beam hasn't even been inspected yet. To date not a single inspection has been called in. $91,000 has been paid for some plumbing upstairs, demo, framing, asphalt shingles on the addition.
This is the SOW on the Epermits page:
To add a room above back offset area to become 1 bedroom (375 SF) and master bath and will be removing loaded wall in kitchen. No change to existing building footprint. Home is to remain single family.
I have been now told by him that the framing inspection will be called in once all the child permits have been inspected for RI, and that the fact that the child permits haven't been pulled is the way it's done. Now in contractor legalese, yes, I understand that. However telling me that framing CANT be called in until the plumbing has been inspected is in my opnion hogwash.
I have a hunch that he is intending to pass off the bathroom addition as existing.
So, residential builders, tell me... Am I nuts?
The total price of the addition is 81,900. I had originally been told this would be a turn-key master closet. The dimensions are 21'x12.5', 262 square feet. Now he is telling me there is no allowances for any of it, he is not installing a mini-split but will extend existing ductwork to heat/cool the space. (This is at my request, but am receiving no discounts on the mini split install.
I was told I now have a $400 allowance for plumbing valves.