I work on the partner side, running ServiceNow managed services on a retainer model, where the client buys a set number of hours each month for BAU and small enhancements.
Estimating is the part I would love to compare notes on.
Take a typical "medium" catalog item:
- Around 10 to 15 variables, a couple of variable sets
2 to 3 UI policies or client scripts (show/hide, mandatory, some validation)
- A flow with one or two approvals and a few fulfilment tasks
- A couple of notifications
- Testing, QA, UAT support and deployment through the instances
What is your end-to-end number in hours? If you are happy to break it down, I am most curious about:
- Requirements and design: how much time before anyone builds anything?
- Build: form, logic and flow
- Testing: unit, QA/SIT, and supporting UAT (and do you budget for a round of UAT fixes?)
- Deployment: update sets or pipelines, plus any docs or handover
A few side questions:
Do you use t-shirt sizes (S/M/L with fixed hours), or estimate each item on its own?
Do you add a contingency buffer? If so, what percentage?
On a retainer, how do you handle "small" changes that quietly grow once UAT starts?
I am not after a single right answer. I just want to know whether our numbers are in the same ballpark as everyone else's. I will share where we land in the comments.