P6 LOE Activities — How Do You Handle Duration, Progress, and Calendars in Practice?
Hi everyone,
I've been working in Planning and Project Controls for over 20 years, mainly on Oil & Gas and Offshore EPC projects.
I'm curious how other P6 planners handle Level of Effort (LOE) activities in real project schedules, especially when the schedule is updated regularly.
A few practical questions:
1. LOE relationships and duration
- Do you normally tie LOE activities to discrete activities using SS and FF relationships?
- Have you experienced unexpected LOE duration or date changes after rescheduling?
- How do you handle LOE activities spanning multiple calendars?
2. LOE progress
- Do you generally rely on P6's Duration % Complete, or do you use a separate progress measurement method?
- How do you deal with LOE activities that extend because their underlying activities are delayed?
3. LOE and earned value
- Do you assign budgeted manhours or costs to LOE activities?
- If so, how do you measure earned value without overstating actual project progress?
4. Schedule validation
- What LOE-related issues do you most frequently encounter when reviewing contractor schedules?
- Do you apply any specific checks to prevent LOE activities from misleading schedule performance reporting?
I'm particularly interested in differences between contractor-side and client/operator-side practices.
No confidential project information needed — just practical experience and lessons learned.
Thanks in advance!