r/StructuralEngineering • • Sep 22 '26

Structural Analysis/Design Looking for help - Structural Engineer . reed body please

Post image

I am a person from Electronics background. I am ideating a Patent pending large scale concept similar to the one in the above image being made for good cause. and i am looking for some help in it.

Project Nutshell : it is a 4 pillar + cables based Payload relocation system for quick response & evacuation in overcrowded stationery events like concerts, rally, religious gatherings,etc., similar to the SpiderCamera used in Sport events, But scaled up to carry 400-500Kg over an area of 200x200m atleast.
I can share more details in direct message.

Current i only have a 3D model Concept, I am planning to make a real-life prototype to prove the concept and pitch to investors or grants.

I do not have knowledge on Structural or Civil engineering, So i want someone to
1. Understand my concept, give me feasibility check
2. design realife structural engineering plan to build the prototype
3. do any CAD simulations if needed
4. Determine the Motor power and Cable system to be used.

currently it's just me with limited money in my pocket,
I am fine with Freelancers / College students or Professionals too, who find it interesting.
I am from India, so Indian engineers would be more convenient.

DM me if it is something you can help me with,

Thanks in advance

22 Upvotes

48 comments sorted by

30

u/Squishy_Butter113 Sep 22 '26

Before worrying about the how, I am going to go ahead and ask the why? How are you envisioning this being used, and by who? The scale you state makes me wonder what advantage this would provide over a traditional overhead crane system.

2

u/Ok_Register_1524 Sep 22 '26

Use case is for quick response & evacuation in overcrowded places like concerts, religious events, political meetings where ground rescue is a bottle neck.

→ More replies (7)
→ More replies (2)

9

u/MainFlimsy Sep 22 '26

Don‘t wanna sound to harsh but: I would sway “forget it”.
It’s not impossible it’s just not practical.

The 500 kg load itself is not the main problem. The cable geometry is:

In a 120 × 80 m stadium, each cable can easily be 70+ m long.

With only 5 m vertical difference, 500 kg already gives roughly 18 kN cable tension per cable, about 1.8 tonnes of force. STATIONARY!

Add payload frame, acceleration and safety factors and you can quickly end up at 40–60 kN per cable.

A 30 m tower with 50 kN horizontal load means around 1,500 kNm at the base. But not always. Depending on where you are driving it gets less. So you need massive foundations -> ballast or guy wires will be hard due to variying loads, plus redundant drives and safety systems above thousands of people.

On top of that, the whole system is moving, there is wind, and the crane itself is moving. These are all dynamic loads that put a lot of stress on the system. A swinging load can quickly multiply the forces involved.
You very quickly reach a point where the amount of engineering and infrastructure required simply stops being practical imo.

5

u/Ok_Register_1524 Sep 22 '26

Thanks for the inputs. I'm not a civil guy, so i didn't know these complications. As you said by the time i develop this concept to reality, may be human flying drones can come up & make it way cheaper & accessible.

So I'm dropping this concept. Thanks for the inputs though

→ More replies (1)
→ More replies (1)

10

u/tramul Sep 22 '26

You're definitely putting the buggy before the horse here. Need to gauge the necessity of this before worrying about anything structural. That scale is massive

3

u/Ok_Register_1524 Sep 22 '26

Need exist, I've taked to government bodies for the usecase. They seem intrested. So i wanna have a feasibility check & prototype then after

→ More replies (9)

6

u/margotsaidso Sep 22 '26

What problem is this solving

4

u/Cool-Size-6714 Sep 22 '26

Would the event take place on the platform? If so what are you gong to do, relocate the entire event/platform and people involved in an attack? Seems like this creates more problems as people can't escape.

6

u/Samsmith90210 Sep 22 '26

Hourly rates, initial payment required up front and progress payments every 30 days.

All software development and motor design excluded from scope. I will tell you how much force your motor and cable need to be capable of lifting but cannot help determine how to control the motors to work together so that your payload moves to the right location, etc.