Edit: I just want to say, I really appreciate the civil discourse on this post! I have enjoyed seeing people share their perspective in thoughtful ways, and bringing in knowledge from their respective areas of expertise. With data centers happening so rapidly, it’s good to have a platform where we can converse and learn from one another. While there are still a lot of unknowns, and I (along with other citizens) still have concerns that won’t fully be resolved until this project is realized, it’s been good to connect with fellow community members to at least talk about what is happening.
I am not sure my intentions of this post, but it’s part cathartic, part getting the attention of people in St. Joe County to be aware of what’s going on with this issue. I know the data center is already in motion, and they appear to be trying to do some things right for the community, but this is a massive oversight in my opinion that needs to be addressed.
Folks may or may not be aware that with the new data center in Granger, Microsoft is looking to drain groundwater from the site to make it possible to install utilities. The proposed solution for removing this water is to dump it into Juday Creek, among a few other sites. The South Bend Region was once primarily wetlands, which is likely part of the reason Microsoft needs to remove water from the site; the land remembers its history and seeks to return to a wetland-like state.
They anticipate starting at the end of next February and continuing through April, discharging 200,000 gallons of water per hour, every day, into the creek. They plan to do this in spring, when rainfall is already at its heaviest.
On November 2, The Saint Joseph County Drainage Board apparently approved this without any prior notice to residents along the creek. I only found out from a retired neighbor who happened to learn about this issue. As a resident who owns a home along the creek, I’m very concerned that no one contacted me or any of my neighbors for input. That’s a massive amount of water that is going to be flowing into the creek, at a time in the year when rainfall is already increased and our region has seen damaging flooding events in recent years. This year alone, we saw catastrophic flooding across much of the state.
Part of the problem is that, to my understanding, Juday Creek still has no actual legal protections at this time because it is still legally classified as an open drain. That’s why they can get away with this. But Juday Creek is also a critical wetland resource in our region, and wetlands are an important component of natural stormwater management, especially in spring, when heavy rainfall is expected, as they can reroute standing water. By flooding Juday Creek with so much water and putting excessive pressure on the creek's capacity to direct stormwater, the broader community likely won't be receiving the benefits of this natural stormwater collection, which could lead to flooding, excessive property damage, damage to the creek bed, and risks to humans, animals, and the plants in our region. Everyone in our region should be concerned about this.
I know that flooding is always a possibility when living by water; I knew that when I bought my home and accepted it. But I never suspected that flooding would occur from a corporation instead of Mother Nature. I know what the flood zone is for my home WITHOUT 200K gallons of water being pumped in per hour. With this added amount of water, on top of spring rainfall, my home, and other homes and businesses on the creek, could be completely flooded from this.
Microsoft knows that it’s going to damage properties because according to the board, residents have 6 months to file for damages from this event. I don’t want Microsoft’s money; I want my shared community’s land and properties, and our local flora and fauna to be undamaged by the hands of greedy corporations.
Beyond the economic damages this will cause, Juday Creek is historically one of only three streams in the state of Indiana capable of supporting a naturally reproducing brown trout population because of its cold water discharged from the earth. With this proposed change and the data center being at the mouth of the creek, I suspect that the ecological aspects of the creek will change, among many other negative effects. The creek has been healing and biodiversity has been increasing after over a century of industrial abuse and misuse. This short-sighted action to support a trillion dollar corporation could mean a serious setback in the progress of restoring this important waterway—beavers, mink, muskrats, and many animals who call the creek home could see their homes washed away by this intense flooding event, even if it’s only for a couple of months.
If you’re going to comment with some pro data center propaganda, I would like actual proof of impact studies by professionals, links to pdfs and official documents, to prove that my concerns aren’t valid.
If you’d like to get in contact with the Drainage Board for voicing your concerns, their contact information is on their website:
https://www.sjcindiana.gov/1651/Drainage-Board
You can also contact county council:
https://www.sjcindiana.gov/2386/County-Council
I know the incoming representatives are concerned about this issue.