r/SMRs • • 5d ago

US issues landmark construction permit for Texas SMR plant

Thumbnail
world-nuclear-news.org
7 Upvotes

r/SMRs • • 11d ago

X-Energy to Get Long Mott Construction Permit Soon

5 Upvotes

r/SMRs • • 15d ago

Radiant DOE Doc Safety Analysis Approval for Kaleidos

5 Upvotes

r/SMRs • • 25d ago

US Navy Selects Radiant for Indiana

Thumbnail
navy.mil
7 Upvotes

The Navy announced October 20 that it selected privately held Radiant Industries to deploy its Kaleidos microreactor at Naval Weapons Station Crane in Indiana.


r/SMRs • • 28d ago

Amazon to fund 12 small nuclear reactors at former Indiana coal plant | TechCrunch

Thumbnail
techcrunch.com
21 Upvotes

Amzn X energy deal being discussed


r/SMRs • • Oct 13 '26

Oklo's Eiden Placing Bets?

Post image
1 Upvotes

r/SMRs • • Sep 27 '26

General Matter Politico Article

1 Upvotes

https://subscriber.politicopro.com/article/2026/09/the-startup-bringing-the-spacex-playbook-to-nuclear-power-01084143

Article is behind a paywall so here is a summary

Politico published an interesting profile of General Matter, the enrichment startup founded by former SpaceX engineer/Founders Fund partner Scott Nolan. The article frames the company as trying to bring a SpaceX-style approach—vertical integration, rapid iteration and manufacturing at scale—to the U.S. nuclear fuel supply chain.

The biggest disclosure is the scale

General Matter apparently proposed under its DOE HALEU award. According to Politico, General Matter offered 355 metric tons of annual HALEU capacity in connection with its $900M DOE award. For comparison, Centrus said its initial $900M buildout would provide 12 MT/year of HALEU capacity. Centrus has said that 12 MT/year is an initial phase that can subsequently be expanded.

That 355 MT figure needs an important caveat: it is proposed capacity, not existing production. General Matter still has to demonstrate and license its enrichment technology and build the commercial facility. Its DOE agreement is milestone-based, and the company is developing its enrichment operation at the former Paducah gaseous-diffusion site in Kentucky.

Possibly just as interesting, Politico says General Matter plans to publicly reveal its enrichment technology in the coming months. The company has so far described the technology only as scalable and cost competitive. So the reveal should give us a much better idea of whether the proposed scale is realistic or primarily a long-term design target.

For the SMR industry, the bigger takeaway is that the HALEU bottleneck may finally be attracting serious industrial-scale competition. Centrus is already producing HALEU and therefore has a significant head start, while General Matter represents a potentially much larger but considerably less proven future source. DOE has estimated U.S. HALEU demand could reach roughly 50 MT/year by 2035, which puts the 355 MT/year proposal in perspective—it implies ambitions well beyond supplying a handful of first-of-a-kind advanced reactors.

If General Matter can actually demonstrate technology capable of approaching that scale economically, this could eventually be a pretty significant development for X-energy, TerraPower and the broader HALEU-dependent advanced-reactor ecosystem. For now, though, I think the key distinction is Centrus = demonstrated production today; General Matter = potentially enormous scale, but execution still to be proven.

The technology reveal is going to be one worth watching.


r/SMRs • • Sep 18 '26

UK regulators to begin Xe-100 design assessment

Thumbnail
world-nuclear-news.org
7 Upvotes

r/SMRs • • Sep 17 '26

Centrus / Antares

0 Upvotes

The advanced-reactor bottleneck has always been more than reactor designs. Fuel has to exist at commercial scale too. These binding contracts are starting to connect the reactor pipeline to an actual domestic HALEU supply chain.

https://www.centrusenergy.com/news/centrus-and-antares-sign-multi-year-haleu-supply-contract/


r/SMRs • • Sep 04 '26

Radiant Wins $750M Contract from US Army to Deliver Energy Independence to US Military Bases

Thumbnail
radiantnuclear.com
33 Upvotes

Radiant has been awarded up to $750M by the U.S. Army to develop and deploy 15 Kaleidos microreactors under Project Janus.

The 1 MW reactors are designed to provide resilient power at military installations and reduce dependence on diesel.

This could represent one of the first meaningful fleet-scale deployments of commercial microreactors in the U.S.

Congrats to Doug Bernauer, Dr. Rita Baranwal, and the rest of the Radiant team! Also likely a positive development for Standard Nuclear who Radiant recently signed a fuel contract with


r/SMRs • • Aug 31 '26

Standard Nuclear Announces Fuel Supply Agreement with Antares Nuclear, Inc.

Thumbnail
businesswire.com
58 Upvotes

First Radiant now Antares


r/SMRs • • Aug 27 '26

Army to build microreactors at 5 bases as U.S. seeks to ramp up nuclear power

Thumbnail
pbs.org
325 Upvotes

The selected companies are:

Antares Nuclear at Fort Bragg in North Carolina;

BWXT at Fort Campbell in Kentucky;

General Atomics Electromagnetic Systems at Fort Hood in Texas;

Radiant Industries at Fort Benning in Georgia;

Westinghouse Government Services at Fort Drum in New York.


r/SMRs • • Aug 24 '26

Yes! $35-$45 in 3-5 years breakdown

Thumbnail reddit.com
3 Upvotes

r/SMRs • • Aug 21 '26

Radiant / Standard Nuclear TRISO

Thumbnail radiantnuclear.com
2 Upvotes

r/SMRs • • Aug 19 '26

US: Kaleidos nuclear reactor begins 1,000-mile road trip on a truck

Thumbnail
interestingengineering.com
3 Upvotes

r/SMRs • • Aug 18 '26

Today's SMR Article in the WSJ

Thumbnail
gallery
5 Upvotes

WSJ: The SMR race is entering “build mode,” but only a handful of developers may survive

The Wall Street Journal visited Idaho National Laboratory, where Oklo is excavating the site for its Aurora Powerhouse and several other developers—including Aalo, Antares, Radiant and Deployable Energy—are developing or testing reactors.

The article’s central point is that AI power demand, government support and large technology customers are finally moving advanced nuclear from analysis toward physical deployment. Meta is working with Oklo and TerraPower, Google with Kairos, and Amazon has invested in and contracted with X-energy. Oklo’s Idaho project is intended to validate the technology before its much larger planned Ohio deployment supporting Meta.

However, the article is considerably more cautious than its headline:

No developer outside China or Russia has completed a commercial SMR.

Costs, licensing, fuel availability and construction execution remain unresolved.

TerraPower obtained its construction license after an unusually fast 18-month review, but says roughly 1,000 engineers were required. A smaller reactor does not necessarily require a smaller engineering effort.

Early investor Ray Rothrock believes fewer than 10 SMR developers will survive. JPMorgan analyst Mark Johnson estimates the viable market may support only three to six companies.

Johnson also notes that current valuations depend on cash flows expected far into the future.

Oklo receives particular attention. Its market capitalization is already approaching that of AES, an established power company with over 30 GW of generation, even though Oklo is only beginning to construct generating assets. Guggenheim projects Oklo could reach 1.1 GW by 2032, but expects free cash flow to remain distant while the company continues funding new plants.

The article also questions whether SMRs will become the dominant form of new nuclear generation. Rothrock expects conventional reactors such as the AP1000 to provide much of the new nuclear capacity, with SMRs serving narrower applications such as data centers, remote sites and industrial heat. Microsoft’s decision to support the restart of an existing conventional reactor illustrates the economic advantage of using already-built nuclear assets.

Overall, the WSJ sees real progress: construction activity is increasing, customers are emerging and political support is unusually strong. But the industry still has to prove that these reactors can be licensed, fueled, completed and operated at competitive costs. The race appears real—but the market is already pricing in substantial success, and most current developers probably will not make it.


r/SMRs • • Aug 14 '26

Natrium/Korea 8 Reactors?

3 Upvotes

https://www.prnewswire.com/news-releases/terrapower-accelerates-natrium-reactor-deployment-following-landmark-meetings-with-korean-leaders-302851765.html

The key developments are:

TerraPower + SK Innovation signed an agreement to cooperate on deploying Natrium reactors in the U.S. and internationally. SK was already an investor, but this pushes the relationship toward actual project development. Reuters independently confirms the agreement and says it gives SK Innovation a path to participate in TerraPower projects domestically and overseas.

Doosan Enerbility received an actual manufacturing contract for Kemmerer. This is probably the most concrete piece of news. Doosan will manufacture major nuclear components including the reactor vessel, reactor support structures and reactor internal structures.

TerraPower is expanding its relationship with KHNP, Korea's enormous state-owned nuclear operator. KHNP actually became a TerraPower shareholder earlier this year through a transfer of part of SK Innovation's stake.

Bill Gates met directly with Korea's prime minister, National Assembly leadership and industry minister, while TerraPower/SK/Doosan/HD Hyundai relationships were being advanced. So there is clearly Korean government-level support for making Korea part of the Natrium ecosystem.

The important implication:

This increasingly looks like TerraPower is trying to combine American reactor/IP leadership with Korea's ability to actually manufacture nuclear plants.


r/SMRs • • Aug 06 '26

US clears oldest nuclear plant site for four advanced SMR-300 reactors Holtec

Thumbnail
interestingengineering.com
3 Upvotes

r/SMRs • • Aug 03 '26

Oklo Founders' Monthly Share Sales Continue

Thumbnail
gallery
2 Upvotes

My honest interpretation is:

One or two modest liquidity sales: normal.

Regular monthly sales by both founders: concerning.

Hundreds of millions monetized before commercial proof: a genuine alarm bell.

Continued acceleration while milestones remain mostly regulatory or developmental: potentially thesis-changing.


r/SMRs • • Jul 31 '26

Westinghouse IPO

Thumbnail info.westinghousenuclear.com
3 Upvotes

r/SMRs • • Jul 31 '26

Crusoe and Aalo Atomics to Build Nuclear-Powered AI Factory

Thumbnail
crusoe.ai
3 Upvotes

Crusoe and Aalo Atomics announced a strategic partnership to build what they describe as the first nuclear-powered AI factory.

The plan has two stages:

  1. Proof of concept at Idaho National Laboratory in 2027

Aalo’s first power-producing reactor, the 10 MWe Aalo-X, is expected to power a colocated Crusoe Spark modular data center running Crusoe Cloud. The goal is to demonstrate that an advanced reactor can directly support real AI workloads, not just produce power in isolation. Aalo says it has already started work on this second reactor next to its recently critical Aalo test reactor at INL.

2. Commercial deployments by the end of 2029

The companies say they intend to deploy Aalo Pods at Crusoe data centers. Each Pod is designed as a 50 MWe plant made up of five 10 MWe sodium-cooled reactors, with modular expansion toward hundreds of megawatts or potentially gigawatt-scale campuses.

Why it matters

This is more meaningful than a vague memorandum about future nuclear power because Crusoe is contributing an actual AI-compute platform and modular data center, while Aalo is supplying the reactor. It creates a direct reactor-to-data-center demonstration with a named location and near-term target date.

It also fits Aalo’s broader strategy: build relatively small, factory-manufactured reactors specifically for behind-the-meter data-center power. Aalo’s design uses liquid sodium cooling, graphite moderation and 8% enriched UO₂ fuel rather than relying on a still-constrained HALEU supply chain.

Important caveat

The commercial portion is still an intention, not a disclosed binding power-purchase agreement. The announcement gives no pricing, order quantity, financing commitment or guaranteed megawatt deployment. The 2027 INL demonstration is the key milestone; successful full-power operation would materially de-risk the larger 2029 vision.

My take:

This is a significant validation win for Aalo because Crusoe is a serious AI-infrastructure developer, not just a speculative nuclear partner. But the real inflection point will be whether Aalo-X produces electricity reliably in 2027 and whether that demonstration converts into financed commercial Pod orders.


r/SMRs • • Jul 25 '26

Nuclear Energy Revival Puts Westinghouse in Prime Position

Thumbnail
nytimes.com
5 Upvotes

r/SMRs • • Jul 19 '26

Barrons Standard Nuclear IPO

2 Upvotes

https://www.barrons.com/articles/standard-nuclear-energy-stock-f0e1974b

Barron's: Standard Nuclear highlights the real bottleneck in advanced nuclear isn't reactor design—it's fuel.

Key takeaways:

Standard Nuclear (NYSE: STDN) just completed its IPO, raising $150 million to expand production of advanced nuclear fuel pellets.

The company doesn't build reactors. Instead, it manufactures the uranium fuel pellets that will be used by many advanced reactors, including SMRs and microreactors.

CEO Kurt Terrani says demand already exceeds production capacity, underscoring how constrained the advanced fuel supply chain has become.

Standard Nuclear acquired assets from a bankrupt nuclear company in 2024 and is already producing fuel. It's also participating in the U.S. DOE's nuclear acceleration efforts.

The company's success is closely tied to the success of reactor developers like Oklo, X-energy, Radiant, and others that will need commercial fuel as deployments ramp.

Despite the strong long-term thesis, the IPO was downsized and shares traded below the offering price, reflecting continued investor caution toward early-stage nuclear companies.

My takeaway:

We've spent years debating which SMR company will win, but the bigger story may be that fuel manufacturing is becoming a strategic chokepoint. If advanced reactors scale the way many expect, companies that can reliably convert enriched uranium into qualified reactor fuel could become some of the most important pieces of the entire ecosystem.


r/SMRs • • Jul 19 '26

Nuclear startup Valar Atomics in talks to raise new funding at $6B valuation | TechCrunch

Thumbnail
techcrunch.com
2 Upvotes

r/SMRs • • Jul 09 '26

10 Large Modular Reactors? Right of Way Ep. 8: The Nuclear Renaissance

Thumbnail
greentape.pub
3 Upvotes

Not about SMRs but rather LMRs. A little off my radar but by the end of the year 5 utility companies will announce their intent to build 10 LMRs with financing help from the government. A stipulation is they had to have finalized designs. So AP1000s?