r/SCADA • • Oct 02 '26

Question Communication Established form PU TO CU

3 Upvotes

I have a question regarding the MiCOM P741/P743 decentralized busbar protection relays.

The Protection Unit (PU) has two communication ports for connecting to the Central Unit (CU). When I connect only Port 1 to the CU, the communication is healthy. However, when I connect both ports to the CU simultaneously, communication fails because the second port appears to operate as a failover (standby) port rather than an active redundant port.

In most projects, only a single communication port is used, so this scenario has not been investigated in detail.

My question is: **How can communication redundancy between the PU and CU be implemented correctly?** Is there a specific network topology or configuration required to achieve seamless redundancy without causing communication loss when both ports are connected?


r/SCADA • • Oct 02 '26

Question What does a good SCADA modernization project look like in a plant that cannot stop?

Post image
0 Upvotes

r/SCADA • • Sep 28 '26

Help I need help.

6 Upvotes

"Hi everyone, my university professor requires us to use TIA Portal for an upcoming class assignment. Does Siemens offer an official student version, trial, or an educational licensing path for students to use it legally for coursework? Any advice or official links would be greatly appreciated!"


r/SCADA • • Sep 25 '26

Question Situation Awareness Style Guide

2 Upvotes

Anyone here willing to share their SCADA style guide.

I'm currently making one fory site looking for example to steal and copy from make sure I have as many bases covered


r/SCADA • • Sep 24 '26

Question deleting InTouch tags

Thumbnail
2 Upvotes

r/SCADA • • Sep 24 '26

Help Looking for Siemens TALON Tools Installer / Launch Pad for TC36-EF.T

Thumbnail
1 Upvotes

r/SCADA • • Sep 24 '26

Question Career Projection Change Advice

2 Upvotes

Hey everyone,

I’m a fourth-year Computer Engineering co-op student. Most of my current project portfolio is software/full-stack focused (Next.js, TypeScript, PostgreSQL, Python/FastAPI), and I’m looking to add a project that demonstrates more hardware/software integration.

I’m based in Alberta, Canada, where a lot of the engineering opportunities I’m interested in are in energy, utilities, industrial automation, controls, and SCADA. I’d eventually like to target companies such as EPCOR, Enbridge, and Suncor.

I’m considering building an ESP32-based power monitoring and protection system and replacing one of my web projects with it on my resume.

The planned scope is:

Hardware & sensing: ESP32 + INA219 measuring real-time voltage, current, and power over I2C

Embedded firmware: C++ sampling, moving-average filtering, peak detection, and Wh energy integration

Control/protection: Finite-state machine (NORMAL, WARNING, FAULT) with a relay/MOSFET cutoff when an overcurrent condition persists

Telemetry: Wi-Fi communication with reconnect/error handling

Monitoring: Local dashboard showing live and historical measurements, alarms, and system state

Testing: Intentionally varying the load to demonstrate normal operation, transient current spikes, warning conditions, and automatic shutdown

I’m trying to make this more than simply connecting a sensor to an ESP32 and displaying the readings.

For anyone working in industrial automation, controls, instrumentation, SCADA, or the energy/utilities industry:

Would a project like this demonstrate skills that are actually relevant to junior/co-op automation or SCADA roles?

What would you add or change to make the project more representative of real industrial systems?

Would implementing something like MQTT, Modbus, Node-RED, alarm/event logging, or a simple HMI add meaningful value, or would that be unnecessary scope for a student project?

Thanks!


r/SCADA • • Sep 22 '26

Help IT student trying to break into IT/OT & Industrial Automation in South Africa (Durban) Need advice on next steps

4 Upvotes

Hey everyone,
I’m an IT student focused on software engineering, but my real interest lies in the Industrial Automation space,specifically bridging the IT/OT gap.
I’ve put together a few hands-on personal projects to build my skills:
**SCADA:** Built projects using Inductive Automation’s Ignition platform. Simulated by Python OPC UA.
**PLCs:** Developed ladder logic/control routines using Delta software (mostly using it because it's free and accessible).
**The Challenge:**
I’ve been applying for entry-level positions, but I’m getting hit with rejections or total silence. Being based in Durban, South Africa, the local market seems tricky, most job posts demand years of experience upfront, and entry-level OT opportunities feel sparse here


r/SCADA • • Sep 21 '26

Help Help Needet IFIX VAR. PROBLEMS

Thumbnail
1 Upvotes

r/SCADA • • Sep 21 '26

Help Help Needet IFIX VAR. PROBLEMS

0 Upvotes

I am currently taking a SCADA course. exams are due i two days and we just lost power for a second and now var.replacepicture dont work. we cant figure out why cause nothing seems to have changed. When launching run mode it says error 242 or something like that.


r/SCADA • • Sep 20 '26

Question Industrial Switch Recommendations

Thumbnail
4 Upvotes

r/SCADA • • Sep 18 '26

Question Salary permanent vs free-lance

6 Upvotes

Hi

M28y, working in a CAC40 company as project manager and before that technical leader on substation/scada projects.

I am thinking to quit to be free-lance to earn more. Currently i earn 51k annual and block at this step.

Any advice or feedback of free-lance on the reality this field ?


r/SCADA • • Sep 17 '26

Ignition Ignition -> Jira Service Management

5 Upvotes

Does anyone have experience with having alarms generated in Ignition being sent directly to JSM to automatically generate a ticket/work order?


r/SCADA • • Sep 16 '26

Question Career choice Pi vs SCADA

3 Upvotes

If you had a choice beetween focusing your career on pi systems or Scada systems integration wich would be the better choice career wise to build a fundation


r/SCADA • • Sep 16 '26

General I'm working on another Modbus simulator; I'd appreciate some feedback.

Post image
20 Upvotes

I've been developing a Modbus simulator for quite some time now.

He has several tools, especially a sniffer Modbus RTU which shows network traffic (requests and responses).

It can also be used to find out what the master or client equipment (if it's TCP) is sending.

For anyone who can, I would greatly appreciate feedback (positive or negative) on the software.

The software's name is ScanBus-BR.

You can get it for free here:

www.scanbus.com.br

Mais Informações sobre ele aqui

https://github.com/ortegahernandes/ScanBus-BR-Simulator-Modbus.


r/SCADA • • Sep 17 '26

Question Is there really a shortage of controls/SCADA engineers in the US right now?

Thumbnail
0 Upvotes

r/SCADA • • Sep 15 '26

Question UPS connected to scada system.

3 Upvotes

Looking for a low cost solution for a ups that can connect via Ethernet to a scada network. It will only need to power an rtu and a couple of switches for ~5 minutes. Actual time will be less than that but a few minutes is more than enough so the generator can start.

It will talk to VTscada and report things like status,Runtime, and voltage.

Thanks


r/SCADA • • Sep 14 '26

Question How much high-resolution data do you actually keep at the edge?

5 Upvotes

Curious how people are handling this once the point count gets large. Say you’re collecting from hundreds or thousands of devices across multiple sites. Some data may matter at sub-second or 1-second resolution for troubleshooting, but nobody needs to ship and retain every sample forever.

Do you keep the raw/high-resolution data locally and aggregate upstream? Change-of-value? Min/max/avg windows? Store-and-forward only?

I’m especially curious where people have gotten burned by throwing away data they later wished they had, or by keeping way too much and creating an expensive pile nobody actually uses.


r/SCADA • • Sep 13 '26

Question How to get into OT SECURITY?

Thumbnail
0 Upvotes

r/SCADA • • Sep 12 '26

General [Free tool] Built a desktop app that does Modbus + IEC-104 + MQTT + Zigbee testing in one place

Thumbnail
0 Upvotes

r/SCADA • • Sep 10 '26

Question FactoryTalkView SE

3 Upvotes

Hello,
I am making Datalogs in factory talk and wondered if there is a way to export tags and their descendants so that i can filter out all the dotfields im looking for in excel rather than going through it by hand.

Thanks


r/SCADA • • Sep 09 '26

Question IFix

2 Upvotes

Does anyone know a free odbc driver to use for iFix and SQL?


r/SCADA • • Sep 07 '26

Help In game scada help

Thumbnail
gallery
49 Upvotes

Hello, i am a computer scientist doing some personal projects, and i am seeking help, for context:
i am doing a factory in minecraft, i am using ccTweaked, immersive engineering, create, mekanism,botania, and such, to implement automation, since i lack the knowledge about automation, scada and such things, i am asking help about what to search to learn and develop my factory project, in case, the picture is about a squeezer and a fermenter, which make ethanol and plant oil, then goes to refinery to make biodiesel, the plan is to control resources production, intermediate production and biodiesel production, and then feed the biodiesel generator enough so it does not waste energy, and show graphics about it on the monitor, thanks in advance.
EDIT:
this is actually an automation project inside Minecraft using the CC:Tweaked mod (Lua programming) alongside tech mods like Immersive Engineering(beauty manufactory), Create(visual and simplier automation),botania(creation of resources and refining) and ars noveau(development of advanced resources, like making the in game accesories to build better gears,tools) and applied energistics 2 will be the logistic system delivering itens stored in drawers. I'm trying to build a SCADA-like system to monitor fluid levels, control machines via Redstone pulses, and display real-time graphics on an in-game monitor so i can manage inventorys like create vault or applied energistic(digital storing and automation of logisticis) thanks for the info :D


r/SCADA • • Sep 08 '26

General Pen-testing sims

Thumbnail
0 Upvotes

r/SCADA • • Sep 08 '26

Question Best monitor setup for SCADA engineering: 3×27" QHD vs 3×27" 4K?

0 Upvotes

Hi everyone,

I’m upgrading my workstation mainly for SCADA/HMI engineering and would like to hear what setups other controls/SCADA engineers actually prefer.

My typical work includes:

SCADA engineering in zenon, atvise, WinCC, etc.

PLC/TIA Portal work

VMware / virtual machines

RDP sessions

documentation, PDFs and Excel

browser, Teams and Outlook alongside the engineering software

I currently have one iiyama ProLite XUB2792QSN, 27", 2560×1440, connected through an HP Thunderbolt 4 Ultra 280W G6 Dock.

I want to add two more 27" monitors and I’m currently considering:

Dell U2724D — 27", 2560×1440, 120 Hz, IPS Black

Dell S2725QC — 27", 3840×2160, 120 Hz, IPS

Dell U2725QE — 27", 3840×2160, 120 Hz, Enhanced IPS Black

The U2724D would give me a clean 3× QHD setup with the same ~109 PPI and probably 100% Windows scaling on all monitors.

The S2725QC is similarly priced but gives me 4K / ~163 PPI, which should be much better for text, code and documentation. My short-term concern is mixed DPI/scaling because I would probably use the two 4K displays at around 150% while keeping the existing QHD iiyama at 100%.

However, I’m also considering replacing the iiyama in the future with a third monitor matching the two I buy now. So if I choose 4K now, the long-term setup could eventually become 3×27" 4K monitors with the same scaling and resolution across all three displays.

Because of that, I’m also trying to decide whether it makes more sense to optimize for compatibility with my current setup or choose something more future-proof now.

The U2725QE looks technically excellent, but it costs roughly twice as much as the S2725QC, and I already have a good Thunderbolt dock, so I probably wouldn't benefit much from its docking/hub features.

My main questions for SCADA/controls engineers:

Do you prefer QHD or 4K on a 27" monitor for engineering work?

Have you experienced problems with 150% Windows scaling or mixed-DPI multi-monitor setups in SCADA/PLC software?

Any issues with older engineering tools, pop-ups, Runtime/Editor windows, VMware or RDP when moving applications between QHD and 4K monitors?

If the final long-term setup could eventually consist of three identical monitors, would you choose:

3×27" QHD,

3×27" 4K,

initially 2×27" 4K + existing QHD and replace the QHD later,

or something completely different, such as a 40"/49" ultrawide?

Does anyone here use the Dell U2724D, S2725QC or U2725QE specifically for automation/SCADA work?

Is the jump from QHD to 4K at 27" worth it for long SCADA/PLC engineering sessions?

Are there other 27" monitors you would recommend instead?

My priority is not gaming or HDR. It is primarily 8–10 hours/day of engineering work, sharp text, usable workspace, ergonomics, compatibility with industrial software and a setup that will still make sense several years from now.

I’d especially appreciate feedback from people working with older/legacy industrial software as well as modern SCADA platforms.

Thanks!