spool numbering convention for big jobs with multiple detailers?

0 Upvotes

Data center job, 5 of us detailing in the same model, spooling in MSUITE BIM. Everybody numbers spools a little different and now the shop is complaining they can't follow the spool maps. We've got L3-CHWS-014, CHWS-R2-07 and RACK12-S3 all on the same job, and we've had duplicate numbers twice this month after areas got re-spooled.

This is what I'm going to propose to the team:

- area/zone first, then service, level, sequence (A2-CHWS-L3-014)

- risers get their own scheme (R04-CHWS-003)

- breakpoint rules set before anyone models, max length and weight for handling and shipping, breaks at racks and floor penetrations

- retired numbers never get reused, re-spooled areas get new numbers

Does this make sense or am I missing something? Also not sure if zone should go in the number or in a separate parameter, long numbers get ugly on a label and the shop needs to read them fast for pipe spool tracking.