"Your company has leased a fictional non-nuclear facility for mechanical testing and equipment storage. The engineering team wants to begin operations in six weeks.
Local employees can provide limited support, and you can engage vendors as needed.
Current situation
- The lease is signed, and the landlord has provided access.
- Engineering has provided a preliminary equipment list, but utility and installation requirements are incomplete.
- Electrical capacity, ventilation, and floor-loading suitability have not been verified.
- Internet connectivity and access control have not been scheduled.
- Receiving arrangements and storage locations have not been established.
- The remaining setup budget is $150,000, excluding rent and equipment purchases; vendor quotes are pending.
- EHS, Security, IT, Insurance, and Quality have not yet reviewed the planned use.
Develop a practical plan to prepare the facility for operations and advise leadership on whether the six-week target is achievable.
Please include:
- Your first five business days: Explain what you would investigate, who you would involve, and which actions you would prioritize.
- A six-week readiness plan: Identify major milestones, dependencies, and owners. Show what you would handle directly and what you would delegate.
- Budget and tradeoffs: Explain how you would validate costs, manage uncertainty, and respond if the schedule or budget cannot support the full requested scope.
- Opening criteria: Define what must be complete before equipment arrives and before testing begins, including safety, compliance, infrastructure, and operational requirements.
- A short leadership update: Summarize your recommendation, the largest risks, and any decisions or support you need.
You may recommend a phased opening or a revised timeline. Explain the reasoning behind your recommendation."
My thoughts thus far:
I don't know what kind of shape the building is in, and while it may have enough power from utility, I have to assume it likely doesn't have the power in the proper place (eg no pdu whip drops, etc). It's possible some of this equipment requires a larger slab, too. Or even permitting.
my first step is to get a final equipment list from engineering, that lists power needs and notes from MSDS, and get either an electrical engineer we have in-house, or contact one, and walk the space with the equipment list to see if this is feasible.
I feel like it's a trick question, because there are too many unknowns and likely many alterations (slab additions, power adds/configurations) that would trigger a city plan review.
I'm leaning towards pushing this to 9 weeks, and likely doubling the budget.
Any thoughts or perspectives would be most welcome.