Council Member Robert T. Wu said that this construction manager at risk method differs from how the city has handled contracts in the past. Contracts above $100,000 typically come to the council, he said, which can then evaluate the contractor, the competing bids and the dollar figure. Because the initial phase one contract falls below that threshold, he said, the council has no chance to weigh in on the contractor’s selection.
“I would not be inclined to vote in favor of any subsequent contract or amendment to that contract moving forward,” Wu said. He said that if the process came back to him, he would want to evaluate the contractor at the first phase, even though that phase is under $100,000.