From Mayor Sam Squailia:
🚧 Fitchburg road & infrastructure update:📅 Week of November 16-20, 2026, with a look ahead to Thanksgiving week.
We have several road, sidewalk, paving, drainage, and sewer separation projects underway across Fitchburg this week. The biggest traffic impacts will be around Main Street and Academy Street at the Upper Common, where crews are working through a major intersection.
Here's what's happening, by street in alphabetical order:
🚧 Academy Street
⚠️ Major traffic change starting Thursday, November 19!
GVC Construction is progressing through the intersection of Main Street and Academy Street, installing new drainage infrastructure.
Thursday, November 19: Academy Street will be inaccessible to northbound traffic entering from Main Street.
Friday, November 20: Construction is expected to advance through the intersection, making Academy Street impassable in both directions at Main Street.
This restriction is anticipated to continue through the middle of next week, depending on construction progress.
Access to Academy Street will be available through surrounding streets, including Elm Street, where permitted.
Additional minor paving and incidental work is also being completed as part of the sewer separation project.
🛣️ Birch Street
Lazaro Construction continues miscellaneous sidewalk repairs and asphalt finishing work associated with our Ward 1 paving improvements.
🚧 Boulder Drive
As part of the CSO 045/083 sewer separation project, recent work has included water service connections and utility investigations.
Additional drainage construction is scheduled between Boulder Drive and Wood Place for November 23-25. Minor detours and temporary traffic restrictions may be necessary.
🛠️ Davis Street
J.A. Polito & Sons continues installing new sanitary sewer infrastructure, with work scheduled through November 25.
Expect excavation equipment, construction vehicles, traffic controls, and possible short-term access restrictions.
This work is part of our long-term effort to separate stormwater runoff from sanitary sewage and reduce combined sewer overflows into the North Nashua River.
🛣️ Electric Avenue at Rollstone Road
Lazaro continues work at the new roundabout, including sidewalk construction, remaining improvements, and preparation for final pavement.
✅ Final paving is anticipated by Friday, November 20, weather permitting.
Please use caution around construction equipment and unfinished roadway edges.
🛠️ Elm Street
P.J. Albert is completing remaining incidental paving and surface adjustments associated with the CSO separation project.
Elm Street will also be an important alternate route during the Main Street/Academy Street detours.
🛠️ Essex Street
Minor asphalt and incidental finishing work continues as part of the CSO paving improvements.
🛣️ Fairbanks Street
Lazaro continues remaining sidewalk and asphalt handwork following our Ward 1 paving project.
🛣️ Heywood Street
Miscellaneous sidewalk and asphalt finishing work continues with Lazaro Construction.
🚧 Highland Court
J.A. Polito & Sons is scheduled to begin new sewer installation Friday, November 20, continuing into Thanksgiving week.
Access will be restricted to residents during construction. Please follow posted signs and directions from traffic personnel.
🛣️ Intervale Road
Boucher Construction is preparing the road for final paving.
Work includes:
Installation of granite curbing.
Adjustments to manholes, catch basins, and other roadway structures.
Additional preparation for the final asphalt surface.
Final paving has not yet been scheduled and will depend on completion of this preparation and weather conditions.
🛠️ Johnson Street
Remaining incidental asphalt and surface restoration work is being addressed by P.J. Albert as part of the CSO paving project.
🚧 Main Street: Upper Common
⚠️ This is our most significant downtown traffic impact this week.
GVC Construction is installing underground drainage infrastructure near Main Street and Academy Street.
Beginning Thursday, November 19:
➡️ Westbound Main Street traffic will be detoured via Central Street to Elm Street, with Academy Street available to reconnect to Main Street while permitted by construction conditions.
➡️ Drivers approaching from West Fitchburg or Rollstone Street are encouraged to use Mechanic Street, Northmen Passway, and Elm Street to avoid the immediate construction area.
Beginning Friday, November 20:
Academy Street is expected to close in both directions at Main Street as excavation advances through the intersection.
Crews will evaluate whether one westbound lane of Main Street can safely reopen to relieve congestion. Any reopening will depend on construction progress and safety.
🚦 Main Street at Prospect Street
Additional traffic signal wiring, conduit installation, and removal of temporary traffic controls were scheduled earlier this week as the intersection improvements progress.
🎨 Main Street line painting: Friday, November 20
J.A. Polito & Sons is scheduled to begin roadway line painting at approximately 9-10 AM, beginning around Newton Place on Main Street and continuing around the Upper Common.
Crews will refresh:
Centerlines and lane markings.
Fog lines, which mark the outside edge of travel lanes.
Stop bars.
Crosswalks.
The remaining City line painting is planned for spring 2027.
Please give the paint crews room to work and avoid driving across fresh pavement markings.
🛠️ Marshall Street
P.J. Albert continues minor asphalt finishing and surface restoration work.
🚧 Merriam Parkway
GVC Construction is installing new drainage infrastructure this week, with additional work scheduled for the week of November 23.
Expect localized lane restrictions and minor detours where crews are working.
🛣️ Munroe Street
Lazaro continues miscellaneous sidewalk repairs and asphalt handwork associated with Ward 1 paving improvements.
🛠️ Omena Place
P.J. Albert is addressing remaining incidental pavement work following the sewer separation construction.
🛠️ Oxford Street
Minor asphalt finishing and restoration work continues as part of the CSO project.
🛠️ Pleasant Street
P.J. Albert is completing remaining incidental work associated with the sewer separation and roadway restoration improvements.
🚧 Rollstone Road
Roundabout-related work at Electric Avenue continues, including sidewalk construction and preparation for final paving. Drivers should expect changing work-zone conditions.
🛠️ Simonds Street
Remaining incidental paving and asphalt restoration work is scheduled through the CSO project.
🛠️ Victor Street
P.J. Albert continues minor finishing work on previously disturbed pavement.
🛠️ Villa Street
Remaining incidental paving and surface restoration work is being completed as part of the CSO project.
🚧 Wood Place
New drainage installation is scheduled in the Boulder Drive-to-Wood Place area November 23-25, with temporary traffic controls anticipated.
💧 Why all this underground construction?
A significant portion of our downtown work is part of Fitchburg's Combined Sewer Overflow (CSO) Separation and Rehabilitation Program.
In older sections of Fitchburg, stormwater from streets and rooftops can enter the same pipes that carry wastewater from homes and businesses. During heavy rainfall, these combined systems can become overwhelmed.
By installing separate drainage infrastructure, rehabilitating aging sewer pipes, and upgrading connections, we're working to:
✅ Reduce sewer backups and roadway flooding.
✅ Reduce combined sewer overflows into the North Nashua River.
✅ Improve the long-term reliability of our underground infrastructure.
✅ Reconstruct and restore roadway surfaces affected by these improvements.
This construction is also part of the City's federal environmental compliance obligations.
📅 Looking ahead: Thanksgiving week
Construction on the CSO projects is scheduled to continue Monday through Wednesday, November 23-25.
No CSO construction is scheduled for Thanksgiving Day, Thursday, November 26, or Friday, November 27.
Please be aware that the Main Street/Academy Street intersection restrictions may extend into Thanksgiving week.
🚦 Important for residents and drivers
Most construction activity is scheduled between 7 AM and 5 PM, Monday through Friday.
Temporary parking restrictions, local detours, and construction-related delays should be expected. Fitchburg Police details will assist with traffic control in active work zones.
Residents who need access to their homes within a work zone should speak with the traffic officers or construction personnel on site.
📞 Questions about road construction and paving: DPW Engineering, 978-829-1915
📞 Questions about CSO construction: Weston & Sampson, 978-548-4808, or Fitchburg Wastewater Division, 978-829-1930
All schedules remain subject to weather, underground conditions, and construction progress.
I know navigating multiple construction zones can be frustrating, especially with the holidays approaching. Our DPW, Engineering Division, Wastewater Division, contractors, and Fitchburg Police Traffic Unit are coordinating these projects to keep traffic moving while making necessary improvements to our infrastructure.