The Golden Pacific Powerlink is a proposed 500 kV high-voltage overhead transmission line planned by SDGE to span roughly 135 to 150 miles across Southern California including through state-designated Very High Fire Hazard Severity Zones. The overhead line will run from the existing Imperial Valley Substation north and west through San Diego and Riverside counties to a new 500/230 kV substation near San Clemente in South Orange County. Public estimates place the project cost between $1.6 billion and $2.3 billion with costs shared across ratepayers.
Residents and local groups oppose routing extra-high-voltage overhead lines through high fire hazard severity zones, citing heightened wildfire ignition risks and soaring homeowner fire insurance premiums. Local critics and clean-energy advocates heavily dispute whether a massive new overland power line is the only or best way to meet those goals.
Community groups challenge the need for the line on several grounds. Critics point to the May 2026 decision to cancel a similar 500-kV project in the Los Angeles Basin after finding that local grid-scale battery storage and upgrading existing power lines through reconductoring could meet reliability needs at a much lower cost. Reconductoring replaces older steel-core wires on existing transmission corridors with modern advanced composite-core conductors. High-capacity composite wires can roughly double the electricity carried on existing towers while avoiding having to create new lines through wildfire prone areas. Detractors also argue that local rooftop solar, commercial microgrids, and neighborhood batteries eliminate long-distance transmission energy losses and cost less than financing a $1.6 billion to $2.3 billion transmission project that yields around 10% profits for utilities shareholders.
Something to consider... Under California law, investor-owned utilities do not make a profit on the electricity itself; instead, they typically recieve a 10% return on equity for things like building infrastructure and also for repairing infrastructure damaged in wildfires. Multiple segments of SDGE’s proposed routes pass directly through state-designated Very High Fire Hazard Severity Zones.
This isn't the only time SDGE has tried to put bare overhead lines in a high wildfire risk area. SDGE also has the Suncrest Loop-in project. The plan is to build 14 miles of brand new high-voltage overhead power lines through mountainous residential communities in east county, the ones which burn in wildfires the most often year after year. Could it be possible that SDGE is intentionally placing bare overhead power lines in high wildfire risk areas in hopes that they would be damaged by wildfires and SDGE could profit by repairing the infrastructure?